Which estimation approach do you prefer when planning projects, and why? I've used both, and honestly neither is great. Top-down usually means someone in leadership picks a budget and timeline, and the project team has to play catch-up. Bottom-up feels more realistic, but by the time you've done the detailed math, management has already locked in numbers that don't match.
In practice, I've had to do a hybrid: bottom-up to know the real cost, top-down to keep leadership happy. Otherwise, you either don't get approval, or you walk straight into failure. So in 2025, is anyone actually seeing PMOs let bottom-up estimates stick, or are we all still massaging numbers to fit someone else's spreadsheet?
In practice, I've had to do a hybrid: bottom-up to know the real cost, top-down to keep leadership happy. Otherwise, you either don't get approval, or you walk straight into failure. So in 2025, is anyone actually seeing PMOs let bottom-up estimates stick, or are we all still massaging numbers to fit someone else's spreadsheet?